request for project preparation grant (PPG)

Project Type: Medium-sized Project

the GEF Trust Fund


Submission date: February 19, 2008

Re-submission date:      

GEFSEC Project ID1:      

GEF Agency Project ID:      

Country(ies): Algeria, Tunisia and Libyal

Project Title: Reducing risks to the sustainable management of the NOrth West Sahara Aquifer System (NWSAS)

GEF Agency(ies): UNEP, (select), (select)

Other Executing partners: OSS (Sahara and Sahel Observatory) and national institutions from Algeria (Agence Nationale des Resources Hydrauliques), Libya (General Water Authority), Tunisia (Direction Générale des Resources en Eau)     

GEF Focal Area(s): Medium-sized ProjectInternational Waters, (select), (select)

GEF-4 Strategic program(s): IW SP-3

name of parent/program/umbrella project: MENARID


a. Project preparation Timeframe

Start date

March 2008

Completion date

October 2008


b. project preparation activities ($)

Describe the PPG activities: Activity 1: Preparation of background documents to be used for the project, particularly preliminarily anaysing socio-economic and environmental implication of water extraction and use, which should serve as basis for developing project activities. Activity 2: Development of pilot site activity proposals in consultation with local proponents and naitonal authorities, through consultation at the national and local levels. Activity 3: Organisation of a meeting to agree on the MSP brief, which will include project M&E plan, specific budget and pilot site proposals. In this three-day meeting, based on the background papers, the three countries will agree on the scope of the MSP and modality of implementation of the project will be discussed and agreed upon. Further, project staekdholers will also be identified.

List project preparation activities

GEF Grant

Co-financing

Total

Preparation of technical background papers

30,000

16,000

46,000

Organisation of a partner meeting

10,000

10,000

20,000

Organisation of pilot site consultation

     

20,000

20,000

     

     

     

     

Total project preparation financing

40,000

46,000

86,000


c. PPG Budget Requesting Finance by GEF

Cost Items

Total Estimated Person Weeks (PW)



GEF ($)

Co-financing ($)

Total ($)

Local consultants *

     

30,000

20,000

50,000

International consultants*

     

     

     

     

Travel

10,000

26,000

36,000

Total PPG Budget

40,000

46,000

86,000

* Split between local and international consultants might be indicative and subject to the procurement guidelines of the
Agencies. Additional information regarding consultants should be provided in Annex A.

d. GEF Agency(ies) Certification

This request has been prepared in accordance with GEF policies and procedures and meets the GEF criteria for project identification and preparation.



Dr. Maryam Niamir-Fuller,

Director, UNEP Division of Global Environment Facility Coordination.

GEF Agency Coordinator



Takehiro Nakamura

Project Contact Person

Date: February 19, 2008

Tel. and Email:+254-20-7623886; takehiro.nakamura@unep.org



Name & Signature

GEF Agency Coordinator



     

Project Contact Person

Date: (Month, Day, Year)

Tel. and Email:     



Name & Signature

GEF Agency Coordinator



     

Project Contact Person

Date: (Month, Day, Year)

Tel. and Email:     







Annex A


Consultants Financed by the Project Preparation Grant (PPG)



Position Titles

$/

Person Week

Estimated PWs


Tasks to be performed

Local




Consultants

750

40

Preparation of background technical papers in preliminarily identiying socio-economic and enviornmental implicaiton of water resources management in the shared aquifer system, so that the scope of the MSP can be decided and agreed upon by the countries. The papers will be in support of developing a project project document.

OSS Coordinator

1,000

20

Review the prepared draft papers by consultants and develop a draft project document for review by stakeholders in the project. Develop site activity proposals in consultation with local stakeholders

International




     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     


























1 Project ID number will be assigned initially by GEFSEC. If PIF has been submitted earlier, use the same ID number as PIF.

5

PPG Template, August 27, 2007