54289 v2
Restructuring Status:
Archived
Restructuring Type: CD Approval
Last modified on date : 04/26/2010
1. Basic Information
Project ID & Name
P085112: QUALITY PROTECT (GEF)
Country
Bosnia and Herzegovina
Task Team Leader
Vesna Francic
Sector Manager/Director
Wael Zakout
Country Director
Jane Armitage
Original Board Approval Date
06/07/2005
Original Closing Date:
02/28/2011
Current Closing Date
02/28/2011
Proposed Closing Date [if applicable]
EA Category
B-Partial Assessment
Revised EA Category
A-Full Assessment
EA Completion Date
12/22/2003
Revised EA Completion Date
2. Revised Financing Plan (US$)
Source
Original
Revised
BORR 6.19
6.19
GEFI 4.00
4.00
GEFU 8.90
8.90
GSPN 1.18
1.18
Total
20.27 20.27
3. Borrower
Organization
Department
Location
4. Implementing Agency
Organization
Department
Location
Ministry of Agriculture, Water
Bosnia and Herzegovina
Resources and Forestry
i
5. Disbursement Estimates (US$m)
Actual amount disbursed as of 04/28/2010
2.73
Fiscal Year
Annual
Cumulative
2010 0.00
2.73
Total
2.73
6. Policy Exceptions and Safeguard Policies
Does the restructured project require any exceptions to Bank policies?
N
Does the restructured projects trigger any new safeguard policies? If yes, please select
N
from the checklist below and update ISDS accordingly before submitting the package.
7a. Project Development Objectives/Outcomes
Original/Current Project Development Objectives/Outcomes
The project development objective is to further strengthen the capacity of local utilities and reduce
pollution from municipal sources into the Neretva and Bosna Rivers. The global objective is to reduce
municipal pollution and nutrients in the Adriatic Sea and the Danube Basin. The sub-objectives are: (i)
develop the Wastewater Improvement Plan; (ii) further strengthen the Joint BiH/Croatian Working group,
with coordination from Serbia and Montenegro to implement the Wastewater Improvement Plan; (iii)
develop and implement high-priority, low-cost water capital investments; and (iv) disseminate information
in BiH and the region for replication of project activities at other priority sites in the Balkans.
7b. Revised Project Development Objectives/Outcomes [if applicable]
ii