Notes
Slide Show
Outline
1
Pacific Islands Oceanic Fisheries Management Project
  • MID TERM EVALUATION
  • Governments of Cook islands, Federated Sates of Micronesia, Fiji, Kiribati, Marshall Islands, Nauru, Niue, Palau, Papua New Guinea, Samoa, Solomon Islands, Tonga, Tokelau, Tuvalu, Vanuatu  United Nations Development Programme Pacific Islands Forum Fisheries Agency
2
Consultants
  •  Team Leader: Leon Zann BSc Hons PhD SPEER Consultants 4 Sunderland Street Evans Head, New South Wales 2473 Australia lpzann@hotmail.com


  •   Regional Resource Specialist:  Veikila Vuki BSc MSc PhD PO Box 5214, UOG Station,  Mangilao,  Guam 96913. vuki61@yahoo.co.uk
3
TABLE OF CONTENTS
  • Executive Summary


  • 1. Introduction
  • 2. Project and development context
  • 3. Approach and methodology of Mid-Term Evaluation
  • 4. Results
  • 4.1 Project Impact
  • 4.2 Project Design
  • 4.3. Project Management and Administration
  • 4.4. Project Implementation
  • 4.5. Project Finances
  • 4.6. Lessons learned
  • 4.7. Summary and explanation of findings and interpretations
  • 5. Recommendations
  • 5.1. Corrective actions for the design, implementation, monitoring and evaluation
  • 5.2. Actions to follow up or reinforce initial benefits from the project
  • 5.3. Proposals for future directions underlining main objectives


  • ANNEXES (9)‏


4
SUMMARY OF MAJOR FINDINGS …
  • OFM Project developed to assist Pacific SIDs sustainably manage their oceanic oceanic resources, and conserve ocean biodiversity.


  •  The Project is (unusually) large in scope and complex in design.
  • Spans a vast area, around 40 million sq km of the Central Western Pacific, and
  • Jurisdictions of 15 Pacific Island nations and territories.
  • Multi-governmental, five year project (2005-2010)
  • Funding US$ 11,644,285 from Global Environment Facility (GEF) and US$ 79,091,993 of co-financing from participating countries, regional organisations and other sources.

    Mid-term Evaluation commissioned by GEF Implementing Agency (UNDP) to assess progress, provide feedback on lessons learnt and future directions.
5
"RESULTS : Major Achievements"
  • RESULTS : Major Achievements


  • OFM Project well designed and implemented
  • Significant impact on the immediate regional objectives (i.e. improved OFM in Pacific SIDS, sustainable development of resources)‏


  • Significant contribution to wider global objectives (i.e. management of oceanic fishery and oceanic biodiversity).


  • Capacities of most Pacific SIDS to meet their obligations under the WCTF Convention enhanced
  • Performance and outcomes of the Project highly rated by the WCPF Commission.
6
Results: Major issues
  • Smaller, less developed Pacific SIDs require greater levels of support (currently occurring in some countries through bilateral funding).
  • Capacity-building largely focused on immediate objectives (needs under the WCPF Convention) not long-term …
  • Long-term, more strategic capacity-building required in the future.
  • IUCN Seamounts study: delayed for matters beyond the organisation’s control. Now redesigned and underway. (Current status IUCN: Kevin Passfield)
7

Review: Project management & administration

.
  • Overall - Efficient and effective.
  • UNDP (GEF Implementing Agency): efficient and responsive
    Issues: bureaucratic procedures affected Executing Agency (FFA); some delays in disbursements, issues generally resolved.


  • FFA: very effective in key management/coordination role.
  • Project Coordination Unit (FFA/PCU): effective but under-resourced
    Issues: PCU under-resourced (4-5% of GEF allocation; 0.5% of total!!; 15-20% admin overheads usual)
    Lacks resources for regular country visits, information dissemination etc.


  • SPC: very effective in increasing knowledge of the status of oceanic
    fisheries.
    Issues: a number of countries indicated their desire for greater domestic capacity in monitoring & modelling
8
REVIEW: Financial management
  • FFA procedures efficient and effective

    Issues: Decline in the US$ 2007-mid 2008 created significant problems, requiring some reallocations of budgets.
    Loss in the value of the Project budget and staff (esp SPC’s scientific assessment and monitoring).
  • Loss in the value of the budget effectively managed by increasing co-financing.
  • Recent strengthening of US$ against AU$ (Oct 08: 15%) should reverse this trend in second term.
  • Leverage funding substantial and further external funds expected.
    Will greatly assist sustainability of the Project.
  • NOTE ALSO:
  • OVERALL COST/EFFECTIVENESS, RISK ASSESSMENT AND ADAPTIVE MANAGEMENT RATED HIGHLY.
  • MTE UNABLE TO SEPARATIE/EVATUATE GEF FUNDING COMPONENT BECAUSE OF EXTENSIVE CO-FUNDING.
  • CO-FINANCING AND CONTRIBUTIONS IN KIND OF THE REGIONAL PARTNERS NOT POSSIBLE TO EVALUATE IN MTE.
9
REVIEW: Cross-cutting issues
  • Institutional strengthening: well addressed
  • National development: well addressed
  •  Innovation: well addressed
  •  Gender: not specifically addressed
  •  Equity and human rights: not well addressed
10
LESSON-LEARNT: positive
  • Strong emphasis on planning and design has ensured timely start, high level of cooperation, ‘ownership’, coordination & maximised chances of success.


  • Detailed, prescriptive approach very useful


  • Effective engagement/ownership of stakeholders


  • Reduced risks in implementation by:
  •  -  utilisation of existing resources, organizations and arrangements
  • maximising stakeholder participation and collaboration through partnership arrangements


  • OFM Project process appropriate model for other regional, multi-stakeholder and inter-governmental projects.


11
LESSONS-LEARNT: negative
  • Needs of smaller Pacific SIDS not adequately considered. (Country needs assessment & specific approaches required.)‏


  • \Some key stakeholders not involved (eg USP in capacity-building and SPREP in biodiversity conservation). (Need for wider engagement of CROPS etc. in future)‏


  • Some National coordination (NCCs) inadequate. Limited govt capacities, aid overly bureaucratic, excessive reporting & meetings etc?. (Need for other approaches)


  • Information dissemination inadequate. (Need for wider public information and media programmes to inform and engage other stakeholders (eg  other Government Departments, industry, community NGOs, schools etc.)‏


  • PCU insufficiently resourced for large and complex project. (Need for greater resources to PCU.)


  • Adaptive management limited. Lack of flexibility in budgets. Currency fluctuations. MTE Lags. (Need for great contingency finding in Aid Projects)


  • SUSTAINABILITY: Longer-term financial support to WCPT Commission uncertain. OFM Project does not take a long-term, strategic approach to Commission, esp smaller countries. (Need for long-term strategic approaches)‏
12
5. RECOMMENDATIONS
  • 5.1. Corrective actions for the design, implementation, monitoring and evaluation of the project
  • 5.1.1. Design: The revised design for the IUCN Seamount sub-component Output 1.3.2. should be closely coordinated, integrated with the wider OFM Project objectivities, and be collaborative with other regional research. IUCN Seamount activities should be coordinated by the Principal Investigator, IUCN Oceania Office in Fiji. Activities and outputs should be related to other aspects of the OFM Project such as management options, law reform, compliance, information strategy etc. Where possible, there should be collaboration with other seamount research and management initiatives in the region (e.g. by French research vessel Alise; Japan Fisheries University /USP seamounts research on Koyo Maru).
  • (Notes: refer to IUCN progress report, 17 Oct, Kelvin Passfield.)
13
 
14
 
15

5.1.3. Partnership agreements
16
5.1.4. Monitoring and reporting
17
5.1.5. Coordination
18
5.1.6. Information dissemination
19
5.2. Actions to follow up or reinforce initial benefits from the project
20
5.3. Proposals for future directions underlining main objectives:  5.3.1. New initiatives
21
New project … OFM GEF #5??
22


New approaches needed for small
Pacific SIDS???
23
Sub-regional groupings to provide better support for smallest countries?
24
Other options for small Pacific SIDS …
25
Suggestions for GEF #5? Commence planning now to maintain continuity of current OFM  initiatives.
  • Objectives: Long-term capacity building in OFM in Pacific SIDS.
  • Project development & Consultation: TOR scoped by consultants reporting to the OFM Steering Committee? Details developed by consultants and workshop of stakeholders (eg. OFM experts, Pacific SIDS, regional organisations (e.g. FFA, SPC, Pacific Forum Secretariat, USP, SPREP), potential donors (e.g. GEF, EU, Japan, AusAID) and NGOs (e.g. WWF, Greenpeace, FSPI).


  • Considerations:
  • Build on current OFM Project, partnership agreements etc
  • Take mid (5-10 yr) and long-term (decadal?), strategic and inclusive approach.
  • Greater focus on specific needs of each country in OFM (mid- to long-term)‏
26
GEF #5? Continued …
  • Utilise existing institutions, (e.g. USP, SPREP, other regional and International institutions) …
  • Funding: GEF? EU? multilateral and bilateral aid, private sector contributions.
  • Funding/in kind support: partnership arrangements and contributions (e.g. commitment to additional staff in OFM in Fisheries Departments).
  • Private sector: closer engagement of the private fisheries sector in OFM.
  • Greater focus on science, better understanding of the ecology of the WTP Large Marine Ecosystem, and the status and conservation of its marine biodiversity. This component might be implemented in collaboration with IUCN, SPREP and SOPAC.



27
OTHER MANAGEMENT CONSIDERATIONS & APPROACHES
  • Continuing need for capacity in fisheries management in most Pacific SIDS. (Small size of Fisheries Depts, high turnover of staff, trained staff leave to join regional organisations/migrate, past training in fisheries development, not sustainable use; senior staff cohort approaching retirement etc)‏


  • Decline in fisheries training organisations, declining enrolments (AMC, USP, Nelson Polytechnic, Japan National Fisheries University).


  • Need for specialised training. Need to for training in sustainable (ecosystem-based) fisheries approaches.


  • Need for evaluation of country needs (mid- long-term), identification of appropriate training programs etc.


  • Need for greater engagement of private sector/industry in OFM management. (eg  PNG National Fisheries Authority model)‏
28
END OF PRESENTATION


Grateful acknowledgements to all informants, Barbara, UNDP etc

Questions etc …
29
END
30
RECOMMENDATIONS: 5.1. Corrective actions for the design, implementation, monitoring and evaluation of the project

  • 5.1.1. Design: The revised design for the IUCN Seamount sub-component Output 1.3.2. should be closely coordinated, integrated with the wider OFM Project objectivities, and be collaborative with other regional research.


  • The various IUCN Seamount activities should be coordinated by the Principal Investigator who is to be recruited by IUCN Oceania Office in Fiji.


  • The activities and outputs of the IUCN Seamount research should be related to other aspects of the OFM Project such as management options, law reform, compliance, information strategy etc.


  •  There should be collaboration with other seamount research and management initiatives in the region (e.g. by French research vessel Alise; Japan Fisheries University /USP seamounts research on Koyo Maru).


  • UPDATE: IUCN?


31
 
32
"A second phase (or..."
  • A second phase (or a new project) should be developed for strategic, long-term capacity-building in OFM in Pacific SIDS, and to specifically assist smaller Pacific SIDS and those with governance and other problems.


  • Rationale:
  • The need for continuation and long-term sustainability of the OFM initiatives, and need for more focused assistance to small Pacific SIDS has been raised throughout the MTE.


  • The 2007 Pacific Forum Leaders’ Vavau Declaration calls for long-term, strategic capacity-building in OFM in the Pacific SIDS.
  • Timing:
  • Planning should commence as soon as possible on a new project. Although the details of  this are outside the scope of this MTE, some general suggestions on process are provided.




33
OTHER INITIATIVES? developing new strategies to better assist small island countries?
  • Need:
  • Lack of substantial progress in capacity-building in the smallest Pacific SIDs in the past 30 years, and


  •  Reality that those with very small populations (e.g. under 25,000?)
    will probably always lack the critical mass/human capacity for specialised OFM etc,


  • Alternative approaches should be developed to better assist small Pacific SIDS.


  • Possible mechanisms to develop strategies?
  • Expert group? ‘Think tank’? (eg experts in OFM and international assistance, private sector, donor organisations and ‘problem solvers’ )‏


  • Open forum or workshop? involving country representatives etc.
34
EXAMPLES OF POSSIBLE STRATEGIES FOR SMALL PACIFIC SIDS: (a) Sub-regional groupings to provide support for smaller countries?
  • Need for collaboration to share OFM expertise sub-regionally.


  • Groupings might be based on current FFA sub-groupings of countries with similar challenges, cultures and experiences, with shared EEZ borders
    and shared tuna stocks. Special assistance from historical/regional developed countries.
  • (a) East Sub-Regional Group: Cook Islands, Tokelau, Niue, Tonga, Samoa
    and New Zealand (shared Polynesian culture, political affiliations with New
    Zealand etc.)
    (b) West Sub-Regional Group: Papua New Guinea, Fiji, Solomon Islands,
    Vanuatu (and Australia?)  (Melanesian, larger, more resources, greater capacity)‏
  • (c) North Sub-Regional Group: FSM (Ponape, Yap, Chuuk), Palau and
    Marshall Islands (Micronesian, small countries, former US affiliations), and 
    Nauru, Kiribati and Tuvalu (Micronesian/Polynesian, atoll countries, former
    British affiliations (Australia?)).  (Note: Subgroups (a) and (c) largely comprise small, isolated island countries. There may be benefits in separating the two groups within (c) on geographic
    and cultural grounds.)
35
EXAMPLES OF POSSIBLE STRATEGIES FOR SMALL PACIFIC SIDS:
(B) Attachments to FFA or delegation of some country functions?

  • a national Fisheries staff member might be situated at FFA to look after their country’s interests; or


  • a dedicated (non-national) FFA staff member or consultant might undertake this task; or


  • a number of technical experts within FFA to look after the specific interests of several/all small countries.


  • country responsibilities in OFM which cannot be carried out by small governments might be delegated to FFA (or contracted to private consultants etc)?


36


end of presentation

thanks

questions etc