Unit of measure
* Footnote
Source: Source
5
PCU, FFA
December 2008, FFA Media Officer recruited and assisting
Information dissemination:
(a) the OFM media strategy should be implemented and
there should be a greater focus on dissemination of
information from the OFM Project by the PCU.
(b) the capacity of the OFM/PCU should be increased to
undertake these additional functions. The previously
recommended additional staff member may be charged
with these responsibilities.
.
PCU & UNDP
December 2008
December 2008
Applicability of LFA tool:
A suite of appropriate indicators should be developed
within the Logical Framework to better monitor progress
in Project Outputs and Activities. (and progress in achieving outcomes and impacts)‏
Project reporting:
The OFM Project Coordinator and UNDP Project
Management should undertake an informal review of the
reporting processes and their effectiveness with the view
of reducing the number and/or detail, while maintaining
their effectiveness.
Responsible units
Time Frame
Key actions
Project Implementation