UNDP GEF APR/PIR 2006
(1 July 2005 to 30 June 2006)
|
Official Title: |
Development and Implementation of the Lake Peipsi/Chudskoe Basin Management Programme |
|
Country/ies: |
Russia and Estonia |
PIMS Number |
2296 |
|
Atlas Project Number |
00014623 |
|
Focal Area |
International Waters |
Project Type (FSP/MSP) |
MSP |
|
Strategic Priority |
Institutional Framework for Sustainable Environmental Management and Energy Development |
Operational Programme |
9 – Integrated ecosystems and resources management |
|
Date of Entry into Work Programme |
10/1998 |
Planned Project Duration |
3 (years) |
|
ProDoc Signature Date |
9/12/2003 |
Original Planned Closing Date |
01.01.2006 |
|
Date of First Disbursement |
01/2003 |
Revised Planned Closing Date |
31.12.2006 |
|
Is this the Terminal APR/PIR? |
Yes |
Date Project Operationally Closed (if applicable) |
n/a |
|
Date Mid Term Evaluation[1] carried out (if applicable) |
June 2004 |
Date Final Evaluation carried out (if applicable) |
February 2006 |
|
Dates of Project Visits by UNDP country office |
27.02.2006 – 01.03.2006 |
Date of last visit by UNDP-GEF RTA |
27.02.2006 – 28.02.2006 |
Project Contacts:
|
Title |
Name |
|
Date |
Signature |
|
Project Manager |
Natalia Alexeeva |
|||
|
Government GEF OFP[2] (optional) |
||||
|
UNDP Country Office Programme Manager |
Elena Armand |
|||
|
UNDP Regional Technical Advisor |
Vladimir Mamaev |
Project Summary (as in PIMS and ProDoc)
|
The overall objective of the Project is to develop and start implementation of a Lake Peipsi/Chudskoe Basin Management Program. This includes practical recommendations for the Lake Peipsi/Chudskoe nutrient load reduction and prevention, and the sustainable conservation of habitats and eco-systems in the cross-border regional context. The project ensures strengthening capacity of all stakeholders groups, as well as active involvement of them for preparation of the Management Program. The project substitutes uncoordinated small-scale projects that would be otherwise implemented separately on the Estonian and Russian sides without sufficient coordination, education, and public information component, and without taking into account interests of local stakeholder groups and wider public. |
|
Project Objective and Outcomes |
Description of Indicator |
Baseline Level |
Target Level |
Level at 30 June 2006 |
| Objective: The overall objective of the Project is to develop and start implementation of a Lake Peipsi/Chudskoe Basin Management Programme |
1. Management Programme is developed |
Absence |
Developed Programme |
Done |
|
2. Starting implementation of the Management Programme |
Absence |
Started implementation |
Started | |
| 3. |
||||
| 4. |
||||
| Outcome 1: Lake Peipsi/Chudskoe Basin Management Plan developed and partially implemented |
1.1. Establish project implementation mechanism and develop coordination mechanism for different projects and activities implemented |
Absence |
Done |
Done |
|
1.2. Assess state of environment in the L. Peipsi/Chudskoe Basin and identification of key water management issues/TDA |
Preliminary |
Done |
Done | |
|
1.3. Prepare a program for coordinated surface water monitoring in the two countries using UN ECE guidelines for monitoring and assessment of transboundary lakes |
Absence |
Done |
Done | |
|
1.4. Design a program of measures to reduce nutrient load pollution, including (1) a detailed program of environmental protection measures to reduce the nutrient load (Nutrient Load Reduction Plan); (2) feasibility study and a concept for ecological farming in the L/ Peipsi/Chudskoe Basin; and (3) feasibility study for water- and ecological tourism around the lake. An infrastructure demonstration project in Estonia. |
Absence |
Done |
Done | |
|
1.5. Develop public and NGO involvement plan as a part of the Management Plan |
Absence |
Done |
Done | |
| Outcome 2: National and local institutional capacity strengthened to implement the Management Plan |
2.1. Strengthen institutional capacity of the Commission and the national authorities to implement the Programme |
Low |
Raised |
Raised |
|
2.2. Strengthen capacities of local authorities and stakeholder groups |
Low |
Raised |
Raised | |
|
2.3. Support NGOs in the region |
Some |
Done |
Done | |
|
2.4. Establishment of the Lake Peipsi museum |
Absence |
Done |
Done | |
| Outcome 3: Environmental education and public awareness programs in the region |
3.1. Develop and launch an information, education and communication system |
Absence |
Done |
Done |
|
3.2. Implement two water-related pilot projects |
Absence |
Done |
Done | |
| 4. |
||||
| 5. |
Rating of Project Progress Towards Meeting Objective[3]
|
2005 Rating |
2006 Rating |
Comments | |
|
Project Manager/Coordinator |
S |
S |
All major planned activities are implemented |
|
Government GEF OFP[4] (optional) |
|||
|
UNDP Country Office |
S |
S |
NGO-driven project, the only one in Russian portfolio, has proven to be successful and such a modality could be used in a future for MSPs |
|
UNDP Regional Technical Advisor |
Action Plan to Address Marginal or Unsatisfactory Rating
Where a project has received a rating of MS or U describe the actions to be taken to address this:
|
Action to be Taken |
By Whom? |
By When? |
List the 4 key outputs delivered so far for each project Outcome:
Project outcome is: Improved capacity of national/sectoral authorities to plan and implement integrated approaches to environmental management and energy development that respond to the needs of the poor
|
Project Outcomes |
Key Outputs |
| Outcome 1: Lake Peipsi/Chudskoe Basin Management Plan developed and partially implemented |
1. Lake Peipsi/Chudskoe Basin Management Plan is ready |
|
2. Public and NGO involvement plan prepared | |
|
3. TDA is ready | |
|
4. An infrastructure demonstration project in Estonia/Rapina is completed | |
| Outcome 2: National and local institutional capacity strengthened to implement the Management Plan |
1. Increased networking, cooperation, and communication of the Joint Commission with other relevant commissions and organizations |
|
2. Governments, NGOs, and other stakeholders fully engaged in preparation and implementation of the Management Programme | |
|
3. Lake Peipsi/Chudskoe Council/Forum established as an institutional network that incorporates agencies and stakeholders at different levels of governance across the border to promote a dialogue on water management issues | |
|
4. Lake Peipsi museums are set up on two sides of the lake | |
| Outcome 3: Environmental education and public awareness programs in the region |
1. Public information and awareness system is in place through diverse communication channels and information formats |
|
2. Two water-related pilot projects on eco-tourism in Estonia and Russia | |
|
3. Environmental education program is developed | |
|
4. Publications on Peipsi fishes, birds, life, eutrophication etc. |
Rating of Project Implementation[5]
|
2005 Rating |
2006 Rating |
Comments | |
|
Project Manager |
S |
S |
All major planned activities are implemented |
|
Government GEF OFP[6] (optional) |
|||
|
UNDP Country Office |
S |
S |
|
|
UNDP Regional Technical Advisor |
Action Plan to Address Marginal and Unsatisfactory Ratings
Where a project has received a rating of MS or U describe the actions to be taken to address this:
|
Action to be Taken |
By Whom? |
By When? |
1. Please annex to this report a print out of the corresponding Atlas Risk Tab (please use landscape format and only print the frame).
2. For any risks identified as “critical” please copy the following information from Atlas:
|
Risk Type |
Date Identified |
Risk Description |
Risk Management Response |
Please report any adjustments made to the project strategy, as reflected in the logical framework matrix, since the Project Document signature:
|
Change Made to: |
Y/N |
Reason for Change |
|
Project Objective |
N |
|
|
Project Outcomes |
N |
|
|
Project Outputs/ Activities / Inputs |
Y |
Nutrient Load Reduction Strategy was developed only for the Estonian part of the basin due to the absence of input (data) from the EU TACIS project in Russia. |
Please present all financial values in US$ millions to 2 decimal places only (eg. $3,502,000 should be written as $3.50m)
|
Name of Partner or Contributor (including the Private Sector) |
Type[7] |
Amount committed in Project Document[8] |
Additional amounts committed after Project Document finalization8 |
Estimated Total Disbursement to 30 June 2006 |
Expected Total Disbursement by end of project |
|
GEF Contribution |
GEF |
$1.00m |
0 |
$1.00m |
$1.00m |
|
Cash Cofinancing – UNDP Managed |
|||||
| UNDP (TRAC) |
UN Agency |
||||
|
Cash Cofinancing |
|||||
|
TACIS project “Water management for Chudskoe lake” |
Multilateral donor |
$1.82m |
$0.58m |
$2.40m |
$2.40m |
|
LIFE-Environment project „Viru and Peipsi catchment area management plan“” |
Multilateral donor |
$0.17m |
$1.83m |
$2.00m |
$2.00m |
|
EU FP 5 “Integrated Strategies for the Management of Transboundary Water on the Eastern European fringe” |
Multilateral donor |
$1.44m |
0 |
$1.44m |
$1.44m |
| Danish EPA |
Government |
$0.665m |
0 |
$0.665m |
$0.665m |
| Peipsi CTC |
NGO |
$0.03m |
$0.07m |
$0.1m |
$0.1m |
|
In-Kind Cofinancing |
|||||
|
Estonian Ministry of Environment |
Government |
$0.64m |
0 |
$0.64m |
$0.64m |
|
Russian Ministry of Natural Resources |
Government |
$0.04m |
0 |
$0.04m |
$0.04m |
|
Total Cofinancing |
$4,805m |
$2.48m |
$7.285m |
$7.285m | |
|
Total for Project |
$5.805m |
$2.48m |
$8.285m |
$8.285m |
Comments
Please explain any significant changes in project financing since Project Document signature, or differences between the anticipated and actual rates of disbursement:
|
Differences in the EU financing are caused by the USD/EURO rate fluctuations and changes in the satellite projects implementation. |
This section only needs to be completed if the project provides funds to any Financial Instruments such as: Trust Funds, Sinking Funds, Revolving Funds, Partial Credit Risk Guarantees, Microfinance services, Leasing or Insurance mechanisms.
If this project does not use any Additional Financial Instruments skip this and go to Section VIII.
|
Financial Instrument |
Financial Institution Responsible for Management |
Basis for Selection of Financial Institution |
For Each Financial Instrument please complete the following two tables:
|
Name of Financial Instrument: |
|
Source of Funds (add rows for each source) |
Funds Committed in Project Document |
Amount Disbursed to Date |
Issues or Comments |
| GEF |
|||
Rating of Performance of Financial Instrument[9]
|
2005 Rating |
2006 Rating |
Comments | |
|
Project Director |
|||
|
Government GEF OFP |
|||
|
UNDP Country Office |
|||
|
UNDP Regional Technical Advisor |
|||
|
Overall Rating |
Action Plan to Address Marginal and Unsatisfactory Ratings
Where a project has received a rating of MS or U describe the actions to be taken to address this:
|
Action to be Taken |
By Whom? |
By When? |
End of Project Situation
What is to happen to any funds remaining in the Financial Instrument at the end of the project?
|
No any funds were left from the project budget after implementation. |
Note : For projects or project components executed by UNOPS this section must not be filled in - data will be provided by UNOPS headquarters.
Please report the US$ value (in Thousands, e.g. 70,000 = 70) ) of UNDP/GEF Payments made to GEF Donor Countries for Procurement. Please enter Project expenditure accumulated from project start up to the date of this report into the matrix against the donor country supplying the personnel, sub-contract, equipment and training to the project. Please report only on contracts over US$ 2,000.
|
Supplying Donor Country |
Personnel (US$ thousands) |
Sub-contracts (US$ thousands) |
Equipment (US$ thousands) |
Training (US$ thousands) |
Total (US$ thousands) |
|
Estonia |
182,1 |
143,6 |
52,4 |
52,5 |
430,6 |
|
Russia |
103,6 |
64,1 |
24,9 |
25,4 |
218 |
|
Norway |
43,0 |
43,0 | |||
| Total |
285,7 |
250,7 |
77,3 |
77,9 |
691,6 |
Are there any lessons from this project that could benefit the design and implementation of other GEF-funded projects? Please list up to three and indicate which one/s could be worth developing into case studies of good/bad practice.
i) Coordination with other in-region projects (implemented as co-financing to the GEF project) requires a lot of time and demands extra resources – so, it is highly recommended to allocate special resources for cooperative activities and plan relevant time for executing such tasksUNDP/GEF Project was closely working with two satellite projects financed by the EU and this experience could be chares with other projects. |
ii) Experience exchange with other transboundary water basins is very useful in terms of networking and getting lessons learnt and best practices from colleagues |
iii) Relevant stakeholders involvement and active public participation in the decision-making processes are essential for the efficient project implementationLake Peipsi/Chudskoe region is well-known due to developed public activities so project experience could be replicated and developed into a case-study. |
Activities under this operational program provide benefits in multiple focal areas and the benefits are achieved through integrated approaches that emphasize better land and water resource management practices. The goal of this operational program is to help countries prevent damage to threatened, but not yet highly degraded, transboundary water systems.
So, this goal was fully covered by the project activities since integrated approach was used for the Management Programme, covering both surface and ground waters, biodiversity issues and joint fish stocks management questions; basin approach was also used in all documents in order to ensure proper integrated water resources management in this transboundary region.
| Unit: |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| RUS10 |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Award ID: |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 00014623 |
PIMS2296 IW MSPLake Peipsi/Chudskoe Management Programme |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Institution: |
Institution Type: |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 02671 |
Peipsi Center for Transboundar |
UNDP |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Award PI: |
Sponsor: |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 634419 |
ARMAND,Elena A |
00012 |
UNITED NATIONS DEVELOPMENT PROGRAMME |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
[1] If an evaluation has been carried out in the last 12 months the report should be attached to this document.
[2] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.
[3] Ratings: See instruction sheet for definitions of ratings. Use only:
HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.
[4] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.
[5] Ratings: See instruction sheet for definitions of ratings. Use only:
HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.
[6] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.
[7] Specify if: UN Agency, other Multilateral, Bilateral Donor, Regional Development Bank (RDB), National Government, Local Government,NGO, Private Sector, Other.
[8] Planned amounts are those shown in the approved Project Document. These may be zero in the case of new leveraged project partners.
[9] Ratings: See instruction sheet for definitions of ratings. Use only:
HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.