UNDP GEF APR/PIR 2006

(1 July 2005 to 30 June 2006)

I. Basic Project Data

Official Title:

Development and Implementation of the Lake Peipsi/Chudskoe Basin Management Programme

Country/ies:

Russia and Estonia

PIMS Number

2296

Atlas Project Number

00014623

Focal Area

International Waters

Project Type (FSP/MSP)

MSP

Strategic Priority

Institutional Framework for Sustainable Environmental Management and Energy Development

Operational Programme

9 – Integrated ecosystems and resources management

Date of Entry into Work Programme

10/1998

Planned Project Duration

3 (years)

ProDoc Signature Date

9/12/2003

Original Planned Closing Date

01.01.2006

Date of First Disbursement

01/2003

Revised Planned Closing Date

31.12.2006

Is this the Terminal APR/PIR?

Yes

Date Project Operationally Closed

(if applicable)

n/a

Date Mid Term Evaluation[1] carried out

(if applicable)

June 2004

Date Final Evaluation carried out

(if applicable)

February 2006

Dates of Project Visits by UNDP country office

27.02.2006 – 01.03.2006

Date of last visit by UNDP-GEF RTA

27.02.2006 – 28.02.2006

Project Contacts:

Title

Name

E-mail

Date

Signature

Project Manager

Natalia Alexeeva

Natalia@ctcspb.ru

Government GEF OFP[2]

(optional)

UNDP Country Office Programme Manager

Elena Armand

Elena.armand@undp.org

UNDP Regional Technical Advisor

Vladimir Mamaev

vladimir.mamaev@undp.org

Project Summary (as in PIMS and ProDoc)

The overall objective of the Project is to develop and start implementation of a Lake Peipsi/Chudskoe Basin Management Program. This includes practical recommendations for the Lake Peipsi/Chudskoe nutrient load reduction and prevention, and the sustainable conservation of habitats and eco-systems in the cross-border regional context. The project ensures strengthening capacity of all stakeholders groups, as well as active involvement of them for preparation of the Management Program. The project substitutes uncoordinated small-scale projects that would be otherwise implemented separately on the Estonian and Russian sides without sufficient coordination, education, and public information component, and without taking into account interests of local stakeholder groups and wider public.


II. Progress towards achieving project objectives

Project Objective and Outcomes

Description of Indicator

Baseline Level

Target Level

Level at 30 June 2006

Objective:

The overall objective of the Project is to develop and start implementation of a Lake Peipsi/Chudskoe Basin Management Programme

1. Management Programme is developed

Absence

Developed Programme

Done

2. Starting implementation of the Management Programme

Absence

Started implementation

Started
3.
4.
Outcome 1:

Lake Peipsi/Chudskoe Basin Management Plan developed and partially implemented

1.1. Establish project implementation mechanism and develop coordination mechanism for different projects and activities implemented

Absence
Done
Done

1.2. Assess state of environment in the L. Peipsi/Chudskoe Basin and identification of key water management issues/TDA

Preliminary
Done
Done

1.3. Prepare a program for coordinated surface water monitoring in the two countries using UN ECE guidelines for monitoring and assessment of transboundary lakes

Absence
Done
Done

1.4. Design a program of measures to reduce nutrient load pollution, including (1) a detailed program of environmental protection measures to reduce the nutrient load (Nutrient Load Reduction Plan); (2) feasibility study and a concept for ecological farming in the L/ Peipsi/Chudskoe Basin; and (3) feasibility study for water- and ecological tourism around the lake. An infrastructure demonstration project in Estonia.

Absence
Done
Done

1.5. Develop public and NGO involvement plan as a part of the Management Plan

Absence
Done
Done
Outcome 2:

National and local institutional capacity strengthened to implement the Management Plan

2.1. Strengthen institutional capacity of the Commission and the national authorities to implement the Programme

Low
Raised
Raised

2.2. Strengthen capacities of local authorities and stakeholder groups

Low
Raised
Raised

2.3. Support NGOs in the region

Some
Done
Done

2.4. Establishment of the Lake Peipsi museum

Absence
Done
Done
Outcome 3:

Environmental education and public awareness programs in the region

3.1. Develop and launch an information, education and communication system

Absence
Done
Done

3.2. Implement two water-related pilot projects

Absence
Done
Done
4.
5.

Rating of Project Progress Towards Meeting Objective[3]

2005 Rating

2006 Rating

Comments

Project Manager/Coordinator

S

S

All major planned activities are implemented

Government GEF OFP[4]

(optional)

UNDP Country Office

S

S

NGO-driven project, the only one in Russian portfolio, has proven to be successful and such a modality could be used in a future for MSPs

UNDP Regional Technical Advisor

Action Plan to Address Marginal or Unsatisfactory Rating

Where a project has received a rating of MS or U describe the actions to be taken to address this:

Action to be Taken

By Whom?

By When?


III. Progress in Project implementation

List the 4 key outputs delivered so far for each project Outcome:

Project outcome is: Improved capacity of national/sectoral authorities to plan and implement integrated approaches to environmental management and energy development that respond to the needs of the poor

Project Outcomes

Key Outputs

Outcome 1:

Lake Peipsi/Chudskoe Basin Management Plan developed and partially implemented

1. Lake Peipsi/Chudskoe Basin Management Plan is ready

2. Public and NGO involvement plan prepared

3. TDA is ready

4. An infrastructure demonstration project in Estonia/Rapina is completed

Outcome 2:

National and local institutional capacity strengthened to implement the Management Plan

1. Increased networking, cooperation, and communication of the Joint Commission with other relevant commissions and organizations

2. Governments, NGOs, and other stakeholders fully engaged in preparation and implementation of the Management Programme

3. Lake Peipsi/Chudskoe Council/Forum established as an institutional network that incorporates agencies and stakeholders at different levels of governance across the border to promote a dialogue on water management issues

4. Lake Peipsi museums are set up on two sides of the lake

Outcome 3:

Environmental education and public awareness programs in the region

1. Public information and awareness system is in place through diverse communication channels and information formats

2. Two water-related pilot projects on eco-tourism in Estonia and Russia

3. Environmental education program is developed

4. Publications on Peipsi fishes, birds, life, eutrophication etc.


Rating of Project Implementation[5]

2005 Rating

2006 Rating

Comments

Project Manager

S

S

All major planned activities are implemented

Government GEF OFP[6]

(optional)

UNDP Country Office

S

S

UNDP Regional Technical Advisor

Action Plan to Address Marginal and Unsatisfactory Ratings

Where a project has received a rating of MS or U describe the actions to be taken to address this:

Action to be Taken

By Whom?

By When?


IV. Risks

1. Please annex to this report a print out of the corresponding Atlas Risk Tab (please use landscape format and only print the frame).

2. For any risks identified as “critical” please copy the following information from Atlas:

Risk Type

Date Identified

Risk Description

Risk Management Response


V. Adjustments to Project Strategy

Please report any adjustments made to the project strategy, as reflected in the logical framework matrix, since the Project Document signature:

Change Made to:

Y/N

Reason for Change

Project Objective

N

Project Outcomes

N

Project Outputs/ Activities / Inputs

Y

Nutrient Load Reduction Strategy was developed only for the Estonian part of the basin due to the absence of input (data) from the EU TACIS project in Russia.


VI. Financial Information

Please present all financial values in US$ millions to 2 decimal places only (eg. $3,502,000 should be written as $3.50m)

Name of Partner or Contributor

(including the Private Sector)

Type[7]

Amount committed in Project Document[8]

Additional amounts committed after Project Document finalization8

Estimated Total Disbursement to

30 June 2006

Expected Total Disbursement by end of project

GEF Contribution

GEF

$1.00m

0

$1.00m

$1.00m

Cash Cofinancing – UNDP Managed

UNDP (TRAC)
UN Agency

Cash Cofinancing

TACIS project “Water management for Chudskoe lake”

Multilateral donor

$1.82m

$0.58m

$2.40m

$2.40m

LIFE-Environment project „Viru and Peipsi catchment area management plan“”

Multilateral donor

$0.17m

$1.83m

$2.00m

$2.00m

EU FP 5 “Integrated Strategies for the Management of Transboundary Water on the Eastern European fringe”

Multilateral donor

$1.44m

0

$1.44m

$1.44m

Danish EPA
Government

$0.665m

0

$0.665m

$0.665m

Peipsi CTC
NGO

$0.03m

$0.07m

$0.1m

$0.1m

In-Kind Cofinancing

Estonian Ministry of Environment

Government

$0.64m

0

$0.64m

$0.64m

Russian Ministry of Natural Resources

Government

$0.04m

0

$0.04m

$0.04m

Total Cofinancing

$4,805m

$2.48m

$7.285m

$7.285m

Total for Project

$5.805m

$2.48m

$8.285m

$8.285m

Comments

Please explain any significant changes in project financing since Project Document signature, or differences between the anticipated and actual rates of disbursement:

Differences in the EU financing are caused by the USD/EURO rate fluctuations and changes in the satellite projects implementation.


VII. Additional Financial Instruments used in the Project

This section only needs to be completed if the project provides funds to any Financial Instruments such as: Trust Funds, Sinking Funds, Revolving Funds, Partial Credit Risk Guarantees, Microfinance services, Leasing or Insurance mechanisms.

If this project does not use any Additional Financial Instruments skip this and go to Section VIII.

Financial Instrument

Financial Institution Responsible for Management

Basis for Selection of Financial Institution

For Each Financial Instrument please complete the following two tables:

Name of Financial Instrument:

Source of Funds

(add rows for each source)

Funds Committed in Project Document

Amount Disbursed to Date

Issues or Comments

GEF

Rating of Performance of Financial Instrument[9]

2005 Rating

2006 Rating

Comments

Project Director

Government GEF OFP

UNDP Country Office

UNDP Regional Technical Advisor

Overall Rating

Action Plan to Address Marginal and Unsatisfactory Ratings

Where a project has received a rating of MS or U describe the actions to be taken to address this:

Action to be Taken

By Whom?

By When?

End of Project Situation

What is to happen to any funds remaining in the Financial Instrument at the end of the project?

No any funds were left from the project budget after implementation.


VIII. Procurement Data

Note : For projects or project components executed by UNOPS this section must not be filled in - data will be provided by UNOPS headquarters.

Please report the US$ value (in Thousands, e.g. 70,000 = 70) ) of UNDP/GEF Payments made to GEF Donor Countries for Procurement. Please enter Project expenditure accumulated from project start up to the date of this report into the matrix against the donor country supplying the personnel, sub-contract, equipment and training to the project. Please report only on contracts over US$ 2,000.

Supplying Donor Country

Personnel

(US$ thousands)

Sub-contracts

(US$ thousands)

Equipment

(US$ thousands)

Training

(US$ thousands)

Total

(US$ thousands)

Estonia

182,1
143,6
52,4
52,5
430,6

Russia

103,6
64,1
24,9
25,4
218

Norway

43,0
43,0
Total
285,7
250,7
77,3
77,9
691,6

IX. Lessons

Are there any lessons from this project that could benefit the design and implementation of other GEF-funded projects? Please list up to three and indicate which one/s could be worth developing into case studies of good/bad practice.

i) Coordination with other in-region projects (implemented as co-financing to the GEF project) requires a lot of time and demands extra resources – so, it is highly recommended to allocate special resources for cooperative activities and plan relevant time for executing such tasks

UNDP/GEF Project was closely working with two satellite projects financed by the EU and this experience could be chares with other projects.

ii) Experience exchange with other transboundary water basins is very useful in terms of networking and getting lessons learnt and best practices from colleagues

iii) Relevant stakeholders involvement and active public participation in the decision-making processes are essential for the efficient project implementation

Lake Peipsi/Chudskoe region is well-known due to developed public activities so project experience could be replicated and developed into a case-study.

X. Project Contribution to GEF Strategic Targets in Focal Area

This project was implemented under the OP 9 “Integrated Land and Water Multiple Focal Area Operational Program”, focal area “International Waters”.

Activities under this operational program provide benefits in multiple focal areas and the benefits are achieved through integrated approaches that emphasize better land and water resource management practices. The goal of this operational program is to help countries prevent damage to threatened, but not yet highly degraded, transboundary water systems.

So, this goal was fully covered by the project activities since integrated approach was used for the Management Programme, covering both surface and ground waters, biodiversity issues and joint fish stocks management questions; basin approach was also used in all documents in order to ensure proper integrated water resources management in this transboundary region.


Unit:
RUS10
Award ID:
00014623

PIMS2296 IW MSPLake Peipsi/Chudskoe Management Programme

Institution:

Institution Type:

02671

Peipsi Center for Transboundar

UNDP
Award PI:
Sponsor:
634419

ARMAND,Elena A

00012

UNITED NATIONS DEVELOPMENT PROGRAMME

Find | View All First Show previous row (inactive button) (Alt+,) 1-14 of 14 Show next row (inactive button) (Alt+.) Last

Risk Type

Date Identified

Risk Description

Risk Management

Critical

Add a new row at row 1 (Alt+7)

Delete row (inactive button) (Alt+8)

ENVIRONMENTAL

Add a new row at row 2 (Alt+7)

Delete row (inactive button) (Alt+8)

FINANCIAL

19/10/2005

Financing of the joint measures in the region still to some extend being sought from international donor agencies and national governments fail to cover transboundary externalities while managing joint transboundary waters – addl risk

Risk Management

Add a new row at row 3 (Alt+7)

Delete row (inactive button) (Alt+8)

OPERATIONAL

19/10/2005

Potential impediments to implementation of a joint water management plan under the EU Water Directive principles that are not a part of the Russian water legislation – low risk

Risk Management

Add a new row at row 4 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

Differences in water monitoring programs, water sampling and analysis methods – modest risk

Risk Management

Add a new row at row 5 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

The language barrier – low risk

Risk Management

Add a new row at row 6 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

The workshop and training seminars are badly designed and planned – low risk

Risk Management

Add a new row at row 7 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

Low environmental awareness of the population and stakeholders in the region that can negatively affect implementation of environmental protection measures in the basin – low risk

Risk Management

Add a new row at row 8 (Alt+7)

Delete row (inactive button) (Alt+8)

ORGANIZATIONAL

Add a new row at row 9 (Alt+7)

Delete row (inactive button) (Alt+8)

POLITICAL

19/10/2005

Aggravation of intergovernmental relations between Estonia and Russia – low risk

Risk Management

Add a new row at row 10 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

Low commitment of policymakers, especially the national governments, including Transboundary Estonian Russian Water Commission – low risk

Risk Management

Add a new row at row 11 (Alt+7)

Delete row (inactive button) (Alt+8)

19/10/2005

Low interest among local authorities and stakeholders to environmental protection issues that may result in a low support to the project – low risk

Risk Management

Add a new row at row 12 (Alt+7)

Delete row (inactive button) (Alt+8)

REGULATORY

Add a new row at row 13 (Alt+7)

Delete row (inactive button) (Alt+8)

STRATEGIC

19/10/2005

NGO executed project will remain an NGO project – and will not be taken over by the governments – low risk

Risk Management

Add a new row at row 14 (Alt+7)

Delete row (inactive button) (Alt+8)

X_OTHER



[1] If an evaluation has been carried out in the last 12 months the report should be attached to this document.

[2] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.

[3] Ratings: See instruction sheet for definitions of ratings. Use only:

HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.

[4] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.

[5] Ratings: See instruction sheet for definitions of ratings. Use only:

HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.

[6] If multiple country project Lead country OFP and UNDP Programme Manager to sign-off.

[7] Specify if: UN Agency, other Multilateral, Bilateral Donor, Regional Development Bank (RDB), National Government, Local Government,NGO, Private Sector, Other.

[8] Planned amounts are those shown in the approved Project Document. These may be zero in the case of new leveraged project partners.

[9] Ratings: See instruction sheet for definitions of ratings. Use only:

HS - Highly Satisfactory; S – Satisfactory; MS – Marginally Satisfactory; U – Unsatisfactory.

Converted with Word to HTML.