DRAFT

Mid-Term Evaluation Report

On the UNDP/GEF Project

‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Management Programme

RER/02/G35
June 2004
Evaluators

Dr Peter Whalley – Team Leader

Dr Evgeny Kurashov

Toomas Pallo

Contents

EXECUTIVE SUMMARY i

1 Introduction. 1

1.1 Project Background. 1

1.2 Purpose of the evaluation. 1

1.3 Key issues addressed. 1

1.4 Methodology of the evaluation. 2

1.5 Structure of the evaluation. 2

1.6 Structure of this Report 2

2 The Project and its development context 3

3 Findings and Conclusions. 3

3.1 Introduction. 3

3.2 Key Observations from Stakeholder and Project Staff Interviews. 3

3.3 Project Delivery. 4

3.4 Project Implementation. 5

3.5 Project Finance. 6

4 Issues and Recommendations. 12

5 Lessons Learnt 14

Annex 1 ToR for the Mid-term Evaluation of the UNDP/GEF Project 16

Annex 2 Proposed Approach by Team Leader 24

Annex 3 Mission Report 26

Annex 4 Key Documents Reviewed. 28

Annex 5 Stakeholder Questions. 29

Annex 6 Project Staff Questions. 31


Executive summary

Background

The overall objective of the project is to develop and start implementation of a Lake Peipsi / Chudskoe Basin Management Program including practical recommendations for the Lake Peipsi / Chudskoe nutrient load reduction and prevention and the sustainable conservation of habitats and eco-systems in the cross-border region. The project is substituting uncoordinated small-scale projects that would be otherwise implemented separately on the Estonian and Russian sides without sufficient coordination, education and public information component, and without taking into account interest of local stakeholder groups and wider public.

The main outputs of the project are:

The project is executed by international NGO Peipsi Center for Transboundary Co-operation. Due to the nature of the project the implementation of project activities are done by two Project Implementation Units situated in Tartu, Estonia and Pskov, Russia. Overall management of the project is responsibility of Project Manager situated in St. Petersburg liaison office, Russia.

Purpose

The purpose of this Mid-Term evaluation is to provide an overall assessment of the project and an opportunity to critically assess administrative and technical strategies and issues. The evaluation gives recommendations to improve the potential of the Project to achieve expected outcomes and objectives within the Project timeframe.

Progress

The project has four stated objectives (presented above). An estimate of completion of each of these objectives was given by the Project Manager. These estimates were considered by the Evaluation Team to be consistent with the quarterly reports submitted to UNDP/GEF.

Conclusion

The project ‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Management Program’ is considered by the Evaluation Team to be progressing well according to the current plan and could be classified as a ‘satisfactory – good’ project. The range here indicates that there are certain aspects of the project implementation that are considered to be well executed or ‘good’ (for example, the project management and the team undertaking the work) and some aspects that were considered to be progressing ‘satisfactorily’ (for example the cross-border cop-operation leading to the development and implementation of the management plan which are outside the control of the project team) The project team undertaking the work is considered to have the necessary expertise on both technical issues and project management skills. There are few immediate concerns observed associated with this project, and the main issue here is probably beyond the scope of this project and clearly in the domain of the Governments of Russia and Estonia. However there were a number of points raised by stakeholders and staff that could lead to strengthening of the project. Some of these issues are known to have been addressed recently or are in the process of being addressed.

The following ‘Issues of Concern’ were identified:

Lessons Learnt

This project is meeting or is planning to meet the key objectives presented in the project documents. This is largely due to the effective project management team that is executing the project plus a well designed and specified project plan. Some examples of lessons learnt from this project include:


1 Introduction

1.1 Project Background

The overall objective of the project is to develop and start implementation of a Lake Peipsi / Chudskoe Basin Management Program including practical recommendations for the Lake Peipsi / Chudskoe nutrient load reduction and prevention and the sustainable conservation of habitats and eco-systems in the cross-border region. The project is substituting uncoordinated small-scale projects that would be otherwise implemented separately on the Estonian and Russian sides without sufficient coordination, education and public information component, and without taking into account interest of local stakeholder groups and wider public.

The development objective of the project is to prepare, adopt and launch Lake Peipsi/Chudskoe Basin Management Programme for the nutrient load reduction and the sustainable development of the cross-border region.

The main outputs of the project are:

The project is executed by international NGO Peipsi Center for Transboundary Co-operation. Due to the nature of the project the implementation of project activities are done by two Project Implementation Units situated in Tartu, Estonia and Pskov, Russia. Overall management of the project is responsibility of Project Manager situated in St. Petersburg liaison office, Russia.

1.2 Purpose of the evaluation

The Mid-Term evaluation is intended to provide a comprehensive overall assessment of the project. The mid-term evaluation provides an opportunity to critically assess administrative and technical strategies, issues and constrains associated with large international and multi-partner initiative. The evaluation gives recommendations for to improve the potential of the Project to achieve expected outcomes and meet objectives within the Project timeframe.

1.3 Key issues addressed

1.4 Methodology of the evaluation

An Evaluation Team was appointed by the UNDP/GEF Peipsi project comprising of:

The Mid-Term Evaluation has been undertaken through a combination of processes including a desk study, selected site visits and interviews stakeholders (but not restricted to): Peipsi CTC, UNDP, Government officials of Estonia and Russia on different levels, local municipalities, local NGOs, communities etc.

The methodology for the evaluation covered the following areas:

1.5 Structure of the evaluation

The Mid-Term Evaluation is comprised of a series of documents compiled in this report, consisting of:

1.6 Structure of this Report

This report is divided into a number of key sections following the recommendations presented in the ToR for this mid-term evaluation (see Annex 1). The report is supported by a Annexes.

Annex 1 Terms of Reference for the Mid-Term Evaluation of the UNDP/GEF Project ‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Management Programme.

Annex 2 Proposed Approach by Team Leader to Evaluation

Annex 3 Mission Report

Annex 4 Key Documents Reviewed

Annex 5 Stakeholder Questionnaire

Annex 6 Project Staff Questionnaire

The Responses to the Stakeholder and Project Staff Questionnaire are located in a separate document together with notes from a ‘round-table’ meeting of stakeholders on 17 June 2004.

2 The Project and its development context

Context

Project start and its duration

January 2003, Duration 3 years

Implementation status

On-going

Problems that the project seeks to address

Management Programme ( Strategy Document) and Action Plan prepared and approved by all relevant Estonian and Russian authorities;

Strengthened Capacity of key regional stakeholders (including environmental monitoring infrastructure and data collection and maintenance system);

Networking and information exchange established;

Two pilot projects implemented in Estonia: one on eutrophication reduction through planning water systems in small community and the second one on ecotourism and nature protection (ecological route).

Immediate and development objectives of the project

To strengthen local capacity to implement an agreed international management programme for the protection of Lake Peipsi / Chudskoe.

Main stakeholders

Ministry of Environment – Estonia

Ministry of Natural Resources – Russian Federation

Joint Water Commission

Local and Regional NGOs

Results expected

Management Programme agreed by Russia and Estonia with appropriately trained staff within responsible organisations and enhanced stakeholders involvement in the region.

3 Findings and Conclusions

3.1 Introduction

The assessment of the project’s performance has been evaluated as described above. The report will follow (where appropriate) the layout specified in the ToR, and covers three main areas:

3.2 Key Observations from Stakeholder and Project Staff Interviews.

3.3 Project Delivery

3.4 Project Implementation

3.5 Project Finance


Result Based Indicators to Measure Success of the Project (from project document)

Indicator

Status

The Management Program as an official legal document in Estonia and Russia for implementation of development and environmental protection measures in the Lake Peipsi/Chudskoe Basin.

  • The need for a Joint Programme has been confirmed.
  • Agreement has been reached for a ToR to be prepared to enable a tender to be issued for the Programme.
  • The Management Programme can be considered to be in a ‘preparation phase’
  • The Evaluation Team considered that this work was satisfactory

The coordinated monitoring program gives reliable and calibrated data for the Management Plan and a program of nutrient reduction plan.

  • Joint Monitoring Programme has still not been approved, but two joint sampling missions have been completed.
  • Discussions on the harmonisation of the monitoring are under discussion but a conclusion is still considered to be distant;
  • The preparation of a co-ordinated monitoring programme is considered to be one of the more significant challenges facing the project by the Evaluation Team. A recommendation is made for more active involvement from leading scientific organisations (Russian, Estonian and International) to assist with resolving this issue.

The Joint Commission as a basis for the strategic planning and coordination of different economic, environmental, and social activities that take place in the region use the Management Program developed.

  • The Joint Commission is fully briefed on the activities of the project;
  • The initial concepts of the Management Programme have been discussed with the Joint Commission;
  • The Joint Commission is actively involved in the preparatory phase of the Management Programme;
  • Relevant Joint Commission experts are involved in the project;
  • The Joint Commission will take on the responsibilities of many of the Management Programmes recommendations and they appear to be sufficiently actively involved to ensure that the outputs of this project will address their needs.

The Joint Commission acts as a facilitator for implementation of the Transboundary Water Agreement and in developing strategies for the long-term sustainable development in the region.

  • The Joint Commission operates under international agreement and the project has actively supported initiatives (e.g. financial support for meetings, equipment purchase, publications, etc.)
  • The Joint Commission receive quarterly reports on the project and presentation on the project status are made by the Project Manager;
  • The Joint Commission assists by providing direction for the UNDP/GEF project.

Agreed nutrient load reduction strategy and targets aimed towards ecosystem restoration and incorporating adaptive management approach for changing conditions identified through monitoring program.

  • A strategy is under development. The Estonian part of the strategy will bee completed by the end of 2004. The Russian side is delayed due to slippage of the EC Tacis project which is co-ordinating with the UNDP/GEF project;
  • Problems associated with the harmonisation of the monitoring programmes will have an impact on the agreed nutrient reduction strategy.

River basin authorities and the Joint Commission receive a reliable and adequate environmental data those serve as a basis for the development of the Management Program. This includes data on nutrient load and eutrophication in the lake basin, status of the lake ecosystem, estimates of the riverine loads to the lake, estimate of the pollution sources, retention and buffering capacity in the drainage basin and the lake, and empirical data on the lake water quality.

  • Two joint sampling and analysis missions have been completed to collect data for establishing the status of the Lake. These missions has provided a good basis for the comparison of methods used for sampling and analysis in Russia and Estonia;
  • Whilst differences in approach are not ideal, the available information enables initial estimates of nutrient (and other pollutant) loads to be made.
  • The Evaluation Team recommends that the approach to sampling should be carefully reviewed and comparative data collected in the future

Harmonized monitoring program and information management system for the lake basin developed.

  • Information Management systems are under discussion between Estonia and Russia to agree the data that will be exchanged in the future. These discussions are being conducted with the involvement of the Joint Commission.
  • These discussions can (and should) proceed in parallel to agreements being sought on a harmonised monitoring programme.

Governments, NGOs, and other stakeholders fully engaged in preparation and implementation of the Management Program.

  • This project has already completed many seminars, round-table meetings to provide a good base of understanding within stakeholder communities. There is excellent involvement of interested stakeholders. Key meetings completed include:
    • 16 group interviews with local NGOs
    • Meeting with specialists in region to establish training needs
    • Joint seminar for Joint Water Commission (2003)
    • Seminar with UNECE on Transboundary waters
    • Transboundary Joint Water Commission Meeting (2004)
    • 3 seminars on eutrophication
    • 2 seminars on biological farming
    • 2 seminars on eco-tourism
    • 2 seminars on water management plans
    • 3 seminars to introduce results on water management plans to local authorities;
    • 11 meetings / workshops / seminars to promote the UNDP/GEF project

Web site is operational and widely utilized in lake basin;

  • Web site created (www.peipsi.org/gef) and intranet for project staff and invited stakeholders.
  • The web site was considered by the Evaluation Team to be of significant benefit to the project assisting well with the dissemination of the products of this project.

Regular publications on lake issues broadly disseminated.

  • There have been numerous publications by the project in a wide range of the media. There are regular publications describing the Lake and its problems. These include:
    • Birds on Lake Peipsi / Chudskoe
    • Fish
    • Eutrophication issues
    • Two small grant programmes have been launched to promote environmental and water protection activities in the region.

Increased networking, cooperation, and communication of the Joint Commission with other relevant commissions and international organizations.

  • There have been several events devoted to this topic, with additional activities planned.
  • Key international co-operation activities include:
    • Joint seminar for Estonian – Russian Joint Water Commission and the Finnish – Norwegian Transboundary Water Commission aimed at exchanging experiences (May 2003)
    • Seminar on UNECE Transboundary Convention and the EU Water Framework Directive aimed at Participatory approaches in Europe and the NIS countries to promote co-operation between the Estonian – Russian Water Commission and the Kazakhstan – Kyrgyzstan Transboundary water Joint Commission (June 2003)

“Lake Peipsi/Chudskoe Water Club” functioning as a mechanism for stakeholder involvement in lake management and decision-making processes.

  • Discussions on the establishment of a ‘water club’ or ‘water council’ is actively in progress. These discussions are expected to lead to the drafting of the main concepts of a Lake Peipsi / Chudskoe Water Club.

Water- and ecological tourism program is an environmental protection and local development program that motivates stakeholders to get involved in implementation of the Management Plan.

  • ToR on a feasibility study for water and eco-tourism is under preparation.

Two demonstration projects successfully implemented and monitored which produce measurable reductions in lake nutrient loads; lessons from these pilots broadly disseminated.

  • One project on public water supply and sewerage system in Rapina municipality is due for completion in July 2004;
  • The second project is due to be selected soon.

4 Issues and Recommendations

The project ‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Management Program’ is considered by the Evaluation Team to be progressing well and according to the current plan. The project team undertaking the work is considered to have the necessary expertise on both technical issues and project management skills. There are few immediate concerns observed associated with this project, and the main issue here is probably beyond the scope of this project and clearly in the domain of the Governments of Russia and Estonia. However there were a number of points raised by stakeholders and staff that could lead to strengthening of the project. Some of these issues are known to have been addressed recently or are in the process of being addressed.

The following ‘Issues of Concern’ were identified:

5 Lessons Learnt

This project is meeting or is planning to meet the key objectives presented in the project documents. This is largely due to the effective project management team that is executing the project plus a well designed and specified project plan. Some examples of lessons learnt from this project include:


Annex 1 ToR for the Mid-term Evaluation of the UNDP/GEF Project

“Development and Implementation of the Lake Peipsi/Chudskoe Basin Management Programme”

RER/02/G35

1. Introduction

Standard UNDP/GEF Monitoring and Evaluation requirements

The Monitoring and Evaluation (M&E) policy at the project level in UNDP/GEF has four objectives: i) to monitor and evaluate results and impacts; ii) to provide a basis for decision making on necessary amendments and improvements; iii) to promote accountability for resource use; and iiii) to document, provide feedback on, and disseminate lessons learned. A mix of tools is used to ensure effective project M&E. These might be applied continuously throughout the lifetime of the project – e.g. periodic monitoring of indicators -, or as specific time-bound exercises such as mid-term reviews, audit reports and final evaluations.

In accordance wit UNDP/GEF policies and procedures, projects with long term implementation period or standing at any other critical milestone of project implementation are strongly encouraged to conduct mid-term evaluations. In addition to providing first review of implementation process, this type of evaluation is responsive to GEF Council decisions on transparency and better access of information during the implementation. Mid-term evaluations are intended to identify project design problems and to be conducted by an independent evaluators not associated with the implementation of the project.

Project objectives

The overall objective of the project is to develop and start implementation of a Lake Peipsi/Chudskoe Basin Management Program including practical recommendations for the Lake Peipsi/Chudskoe nutrient load reduction and prevention and the sustainable conservation of habitats and eco-systems in the cross-border region. The project is substituting uncoordinated small-scale projects that would be otherwise implemented separately on the Estonian and Russian sides without sufficient coordination, education and public information component, and without taking into account interest of local stakeholder groups and wider public.

The development objective of the project is to prepare, adopt and launch Lake Peipsi/Chudskoe Basin Management Programme for the nutrient load reduction and the sustainable development of the cross-border region.

The main outputs of the project are:

Project is executed by international NGO Peipsi Center for Transboundary Cooperation. Due to the nature of the project the implementation of project activities are done by two Project Implementation Units situated in Tartu, Estonia and Pskov, Russia. Overall management of the project is responsibility of Project Manager situated in St. Petersburg liaison office, Russia.

2. Objective and purpose of the Mid-term Evaluation

The Mid-Term evaluation is intended to provide a comprehensive overall assessment of the project mid-way. The mid-term evaluation provides an opportunity to critically assess administrative and technical strategies, issues and constrains associated with large international and multi-partner initiative. The evaluation should also provide recommendations for strategies, approaches and/or activities to improve the potential of the Project to achieve expected outcomes and meet objectives within the Project timeframe.

The purpose of the Mid-Term Evaluation is:

The Report of the Mid-term Evaluation will be stand-alone document that substantiates its recommendations and conclusions.

The Report will be targeted to meet the evaluation needs of all key stakeholders (GEF, UNDP, MOE, MNR, Peipsi CTC and other stakeholders of Estonia and Russia).

3. Evaluation

Project elements to be evaluated include:

Project Management and Administration

Project Substantive and Technical Implementation

1. Project Delivery

The evaluation will assess to what extent the Project has achieved its immediate objectives. It will also identify what outputs have been produced and how they have enabled the Project to achieve its objectives.

This section will focus on following priority areas:

Progress of the Project as whole in achieving anticipated outcomes:

Partnership:

2. Project Implementation

The Evaluation Team will be provided with an explanation of the implementation structure of the project by Peipsi CTC and UNDP (on need basis).

This section will focus on following areas of implementation:

Project oversight:

Project Execution (incl. Cooperation between PIU’s):

Monitoring and evaluation:

Risk Management:

3. Project finances

4. Methodology for Evaluation Approach

The Mid-Term Evaluation will be done through a combination of processes including a desk study, selected site visits and interviews - involving all stakeholders (but not restricted to): Peipsi CTC, UNDP, Government officials of Estonia and Russia on different levels, local municipalities, local NGO’s, communities etc.

The methodology for the evaluation is envisaged to cover the following areas:

5. Products

The main product of the Mid-Term Evaluation will be:

Mid-Term Evaluation Report

The final Mid-Term Evaluation report will include:

· Findings and conclusions in relation to issues to be addressed identified under section Evaluation of this TOR;

· Assessment of gaps and/or additional measures needed that might justify further funding to Peipsi/Chudskoe lake region;

· Recommendations for the further implementation.

The draft and final report will be written in the format outlined in Annex 1 of this TOR. The draft report will be submitted to Peipsi CTC no later than 06 of April 2004.

Based on the feedback received from stakeholders a final report will be prepared by 15th of May 2004.

The report will be submitted both electronically and in hard copies.

Presentation of basic information on the project and evaluators’ rating and textual assessment.

Summary presentation of findings to be presented in final evaluation meeting

Team leader will conduct a final meeting for selected stakeholders and prepares summary presentation of conclusions and findings of the Mid-Term Evaluation.

The presentation will be followed by questions&answers session and round-table discussion on effective implementation of evaluation recommendations.

6. Evaluation Team

The Mid-Term Evaluation will be carried out by team of three external consultants:

The team will be lead by International Consultant, who has overall responsibility over successful completion of the evaluation and finalizing Mid-term Evaluation report. The team leader is expected to be familiar with the region and have basic knowledge of the project area (such as transboundary waters, transboundary cooperation etc.)

7. Implementation Arrangements

Evaluation management arrangements

Tentative timeframe

May 2004

Annex 1: Outline of Mid-Term Evaluation Report

Executive summary

Introduction

The Project and its development context

Findings and Conclusions

Recommendations

Lessons learned

Annexes

Other relevant material


Annex 2 Proposed Approach by Team Leader

Mid-Term Evaluation of the UNDP/GEF Project

‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Water Management Programme’

Introduction

These brief notes are prepared on the basis of the Terms of Reference to undertake this evaluation. The work will be undertaken by a team comprising of two National Experts (Russian and Estonian) and an International Expert.

The Terms of Reference (ToR) indicates that the purpose of this evaluation is to:

The review will assess both the Project Management and the technical implementation of the project. The output of this evaluation will be a Mid-Term Evaluation Report that will summarise key issues to be addressed in the execution of the project, assessment of gaps and any additional measures needing funding and recommendations for any further implementation.

Approach Suggested by International Expert

The ToR identifies the key stakeholders that should be involved in this assessment, and these, in combination with reports produced by the project team will provide the base information for the Evaluation Report. The proposed programme for the International Expert is:

Tentative Timescale

Review of documents Early May 2004

Mission to Peipsi Late May 2004

Draft Report Mid June 2004

Final Report End June 2004

Final Presentation Early July 2004

Travel / Missions

Two missions are planned. The first (duration 5 days) to meet key stakeholders and National Experts. The second to present the report / recommendations of the evaluation.

PDW 20/4/04

Annex 3 Mission Report

Mid-Term Evaluation Report

‘Development and Implementation of the Lake Peipsi / Chudskoe Basin Management Programme

RER/02/G35

Mission Report

The Evaluation Team selected was:

Peter Whalley
Toomas Pallo

Evgeny Kurashov

Programme:

The Evaluation Team completed a programme of meetings and discussions with key stakeholders suggested by the Project Team and with the project offices in both Tartu and Pskov (14 June – 18 June 2004).

During this mission two workshops were held in Tartu related to the project. The opportunity was taken by the Evaluation Team to participate in some of these events and to meet participants.

A series of questions were used for seeking information on the performance of the project and its impact on environmental issues in the Lake Peipsi / Chudskoe basin. These questions are presented in Annexes 5 and 6 (of Main Evaluation Report) for stakeholders and project office staff respectively

A ‘round-table’ discussion was held with participants at the Project Meeting (17 June 2004). These were representatives of the Joint Water Commission and Project Steering Group. The following three key objectives of this project were discussed.

Personnel Met

Project Office Staff met

Natalia Alexeeva – Project Manager

Sille Talvet - Project Advisor

Aija Kosk – PIU Tartu – Estonian Project Co-ordinator

Olga Vassilenko – PIU Pskov – Pskov PIU Co-ordinator

Lea Vedder – Financial Manager

Ulo Sults – Water Monitoring Expert

Eilika Molder – Webmaster

Erkki Vedder – Capacity Building Expert

Angelika Rehema – Capacity Building Expert

Elena Bystrova – Capacity Building Expert

Darja Postnova – Webmaster and information expert

Mari Keskkula – Administrative Support

Stakeholders met

Estonia

Harry Liiv – Deputy Secretary General – Environment Protection

Jurgen Kiris – Legal Secretary - Lohusuu Municipal Government

Russia

Mikhail Radinov –Head of Department of Municiple Services – Pskov City Administration

Asja Zamareva – Journalist – Sterkh Newspaper – Pskov

Alexander Evgenevich Shkrebets – IT Expert – NGO TEIA

Elena Alexeevna Armand – Head of Environment Unit UNDP Moscow

Nikolaiy Ivanovich Danilkin – Head of department of Complex Planning – Pskovvodproekt

Ioulia Ronanovna Nefefova – Head of Department of Natural Resources and Environmental Protection – MNR Pskov Region

Marina Viktotovna Kazmina – Head FGU Pskovvodkhoz MNR

Mikhail Livovich Kallistratov – Head of Regulation and Water Use – Pskovvodkhoz

Dmitry Alexandrovich Antonyuk – Centre of Civil Initiatives Support

Evgenij Aleksandrovich Afanasiev – Head GosNIORKH (State Institute of Lake and River Fish)

Participants at the ‘Round-Table’ Meeting 17 June 2004.

Vladimir Budarin - Ministry of Natural Resources (RF)

Alla Sedova - Ministry of Natural Resources (RF)

Svetlana Basova - Ministry of Natural Resources (RF)

Alexander Ovanesyants - Ministry of Natural Resources (RF)

Jalmar Mandel - Ministry of Environment (EE)

Ago Jaai – Ministry of Environment (EE)

Marina Kazmina, Ministry of Natural Resources (RF)

Other Experts

Dr Gulnara Roll – INTAS (former Project Advisor)

Vladimir Skorokhodov – Manager Tacis Local Support Office – St Petersburg

Participants at the two workshops held in Tartu.


Annex 4 Key Documents Reviewed


Annex 5 Stakeholder Questions

UNDP/GEF Lake Peipsi Project – Mid-term Evaluation – Stakeholder Assessment

An important component of this mid-term review is an assessment of stakeholder perception of the progress of this project and their involvement in the project. The stakeholders fall into a number of categories:

  1. International Stakeholders

· UNDP/ GEF

· Peipsi CTC

· Estonian – Russian Trans-boundary Water Commission

· International NGOs

· EC Tacis

· Other international projects

  1. Government Officials

· Estonian Government officials

· Russian Government officials

  1. Local interest

· Local municipalities

· Local Community representatives;

· Local NGOs

· Local projects

This assessment will evaluate the level of collaboration between

The purpose of the interviews will be to establish the level of contact between stakeholders and the project, to establish the ‘value’ placed on the project by the stakeholders and to obtain feedback on the execution of the project. The questionnaire (SHORT!) should be divided into several sections – to establish the role of the person being interviewed and their involvement with Lake Peipsi/Chudskoe and then to establish their perception of the progress of the project, the information being provided by the CTC and the involvement of the public in general in the improvements to the environment as a result of this project.


UNDP/GEF Lake Peipsi Project – Mid-term Evaluation – Stakeholder Assessment

· What is your job function and in what way are you involved in Lake Peipsi/ Chudskoe?

· What is your expectation from the Lake Peipsi/Chudskoe project?

· Please give your views of the benefit of this project from a local/national/international perspective (based on your involvement in the project)

· Are the objectives of the project reasonable and will they lead to the expected environmental benefits? If not, why?

· From your perception, is the Project meeting your anticipated needs? If not, in what way is it failing?

· Do you have contact with other stakeholders involved in the project? If yes who and for what purpose?

· Is the project assisting international co-operation on the Lake Peipsi/Chudskoe? If yes, please give some examples. If not, please give examples of why not and how this could be improved.

· Are the longer term aspects (i.e. beyond the completion of this project) of this project clear? Will the outcome of this project be sustainable? Can you suggest how this sustainability will be achieved?

· Do you have sufficient contact with the Peipsi CTC project team and does this meet your needs? If not, please indicate how often you have contact with CTC (project team)?

· Is the information coming from the Peipsi CTC of sufficient clarity to enable you to monitor the progress of the project? If not how could this be improved?

· Do you think this project is interacting satisfactorily with other national/international projects? If not please explain.

· Is the information provided by the project to the general public of benefit? If not how could this be improved?

· Please provide any suggestions that would enhance the benefit of this project to you or other stakeholders?

· Any other comments?


Annex 6 Project Staff Questions

CTC Office Interviews

Management

  1. Natalia Alexeeva & Sille Talvet
  2. Gulnara Roll
  3. Aija Kosk & Olga Vassilenko
  4. Lea Vedder

Questions:-

Project Management and Administration

  1. List KEY Project administrative documents
  2. List KEY decisions and outputs from project
  3. List KEY Project implementation documents and how they were used.
  4. HOW have these helped support national and trans-national dimensions of project.

Project Substantive and Technical Implementation

  1. What are the projects immediate objectives?
  2. To what extent have these been achieved? (level??)
  3. What estimate of quality can be placed on the Project Activities?

Project Execution (incl. Cooperation between PIU’s):

Monitoring and evaluation:

Risk Management:

3. Project finances

Plus ‘Success Indicators’

Techncial

  1. Ulo Sults
  2. Angelika Rehemaa
  3. Erkki Vedder
  4. Elena Bystrova
Questions:-

Project Support

  1. Eilika Molder
  2. Darja Postnova
  3. Mari Keskkula
  4. Ekaterina Mishina
Questions:-
Converted with Word to HTML.