Overview

Zambia NEX
Tanzania NEX
DRC WWF-UNOPS
Burundi UNOPS
Regional UNOPS


Sheet 1: Zambia NEX

Annex 3 (for Section III in text): TOTAL BUDGET AND ANNUAL WORKPLAN











Award ID:











Award Title: PIMS1941 – IW- FSP- Lake Tanganyika – Zambia Component











Project ID: tbd











Project Title: Lake Tanganyika Integrated Management Programme – Zambia Component











Implementing Partner/Executing Agency: Ministry of Tourism, Environment and Natural Resources
























Activities / Outcomes Resp. Party Fund Code Donor Code Budget Code Budget description Year 1 Year 2 Year 3 Year 4 TOTAL Budget Note
Outcome 1: Reducing levels of siltation into the lake resulting from improved management of the Lake's catchments through sustainable use of agricultural and forest resources Govt of Zamibia 62000 GEF 71200 International Consultant 5,000 5,000 5,000 5,000 20,000 1
71300 Local Consultant 40,000 60,000 68,000 40,000 208,000 2
71400 Locally recruited PMU staff 85,000 85,000 85,000 85,000 340,000 3
71600 Travel 31,000 33,000 33,000 33,000 130,000 4
72800 IT Equipment 6,000 0 0 0 6,000 5
72100 Contractual Services Companies 110,000 120,000 110,000 100,000 440,000 6

Learning 35,000 50,000 50,000 45,000 180,000 7
72200 Equipment and Furniture 27,000 0 0 0 27,000 8
72300 Materials & Goods 0 200,000 300,000 50,000 550,000 9
72400 Communication and AV Equipment 4,000 0 0 0 4,000 10
72500 Supplies 3,000 5,000 5,000 5,000 18,000 11
72600 Grants 0 70,000 70,000 60,000 200,000 12
73400 Rental & Maint of Other Equip 20,000 15,000 15,000 15,000 65,000 13
74200 AV & Printing Production Costs 7,000 10,000 11,000 12,000 40,000 14
74500 Miscellaneous 2,000 2,000 2,000 2,000 8,000


Sub-total OUTCOME 1



2,236,000

Project Management Govt of Zamibia 62000 GEF 71200 International Consultant 0 13,000 0 13,000 26,000 15
71400 Locally recruited PMU staff 15,000 15,000 15,000 15,000 60,000 16
72200 Equipment and Furniture 6,000 0 0 0 6,000 17
72500 Supplies 2,000 2,000 2,000 2,000 8,000 18
72800 IT Equipment 6,000 0 0 0 6,000 19
73100 Rental&Maintenance-Premises 16,000 16,000 16,000 16,000 64,000 20
73200 Premises Alterations 10,000 0 0 0 10,000 21
74100 Professional Services 5,000 5,000 5,000 5,000 20,000 22
74500 Miscellaneous 1,000 1,000 1,000 1,000 4,000


Sub-total Project Management



204,000






TOTAL GEF 436,000 707,000 793,000 504,000 2,440,000














Budget Note:











1 Adaptation Specialist










2 See the activity note for details










3 PMU inputs (85%)










4 Travel to & from LUSAKA (Plus 1,200 km) -Workshops & Consultations; also includes National PSC and PM travel to Regional PSC










5 Laptop, printer and other necessary computer related accessaries for Project Manager










6 Consulting firms for outputs 1&2 & workshops venue hiring










7 consultation, training, awareness raising workshops










8 Project Car










9 Tree seedlings, etc.










10 TV, VCR/DVD, ppt projector for awareness raising










11 papers, etc for workshop










12 For Income Generating Activities Start-up revolving fund (Output 2)










13 Car maintenance (Petrol, insurance, radio subscription, check-up, etc.)










14 for dissemination materials










15 for MTE and TE










16 PMU inputs (15%)










17 Office machinery










18 papers, etc for project management










19 computers for Admin and Finance Assistants










20 Utilities, Security, etc. Rent is covered by the Govt.










21 Office Renovation










22 for NEX audits











Sheet 2: Tanzania NEX

Annex 4: TOTAL BUDGET AND ANNUAL WORKPLAN
























Award ID: tbd











Award Title: PIMS1941 – IW- FSP- Lake Tanganyika – Tanzania Component











Project ID: tbd











Project Title: Lake Tanganyika Integrated Environmental Management Project – Tanzania Component











Implementing Partner/Executing Agency: Tanzania Division of Environment
























Activities / Outcomes Resp. Party Fund Code Donor Code Budget Code Budget description Year 1 Year 2 Year 3 Year 4 TOTAL Budget Note
Outcome1: Sediment flows into Lake Tanganyika from the pilot villages reduced through integrated catchment management, thereby improving lake habitats Govt of Tanzania 62000 GEF 71200 International Consultant 30,000 40,000 39,500 30,000 139,500 1
71300 Local Consultant 80,000 80,000 80,000 78,500 318,500 2
71400 Locally recruited PMU staff 80,000 110,000 100,000 100,000 390,000 3
71600 Travel 27,000 32,000 32,000 31,000 122,000 4

Learning and S/H Workshops 40,000 45,000 45,000 45,000 175,000 5
72800 IT Equipment 20,000 0 0 0 20,000 6
72100 Contractual Services Companies 70,000 80,000 77,000 70,000 297,000 7
72200 Equipment and Furniture 46,000 0 0 0 46,000 8
72300 Materials & Goods 0 40,000 40,000 35,500 115,500 9
72400 Communication and AV Equipment 5,000 0 0 0 5,000 10
72500 Supplies 5,000 5,000 5,000 5,000 20,000 11
72600 Grants 20,000 50,000 50,000 52,000 172,000 12
73400 Rental & Maint of Other Equip 17,000 17,000 17,000 17,000 68,000 13
74200 AV & Printing Production Costs 5,000 15,000 15,000 15,000 50,000 14
74500 Miscellaneous 3,000 3,000 3,000 3,000 12,000


Sub-total OUTCOME 1



1,950,500

Outcome 2: Wastewater Management at Kigoma-Ujiji Township strengthened, leading to the Lake biodiversity improvement Govt of Tanzania 62000 GEF 71200 International Consultant 6,000 7,000 7,000 7,000 27,000 15
71300 Local Consultant 7,000 15,000 15,000 15,000 52,000 16
71400 Locally recruited PMU staff 18,000 20,000 20,000 20,000 78,000 17
71600 Travel 5,000 10,000 13,000 5,000 33,000 18
72100 Contractual Services Companies 10,000 20,000 20,000 20,000 70,000 19
72500 Supplies 2,000 3,000 3,000 2,000 10,000 20
74200 AV & Printing Production Costs 4,000 7,000 8,000 7,000 26,000 21
74500 Miscellaneous 1,000 1,000 1,000 1,000 4,000


Sub-total OUTCOME 2



300,000

Project Management Govt of Tanzania 62000 GEF 71200 International Consultant 0 15,000 0 15,000 30,000 22
71400 Locally recruited PMU staff 13,000 13,000 13,000 13,000 52,000 23
71600 Travel 10,000 0 0 0 10,000 24
72100 Contractual Services Companies 5,000 0 0 0 5,000 25
72200 Equipment and Furniture 8,000 0 0 0 8,000 26
72500 Supplies 5,000 2,000 2,000 2,000 11,000 27
72800 IT Equipment 14,500 0 0 0 14,500 28
73100 Rental&Maintenance-Premises 24,000 24,000 24,000 24,000 96,000 29
73200 Premises Alterations 7,000 0 0 0 7,000 30
74100 Professional Services 3,000 3,000 3,000 3,000 12,000 31
74500 Miscellaneous 1,000 1,000 1,000 1,000 4,000


Sub-total Project Management



249,500






TOTAL GEF 591,500 658,000 633,500 617,000 2,500,000














Budget Notes:











1 See activity notes










2 See activity notes










3 PMU inputs (75%)










4 See activity notes










5 See activity notes










6 Laptop, printer and any other computer related accessaries for Project Manager










7 See activity notes










8 Project Car and a photo copier










9 Stoves, Kilms, Tree seeds, fertilizers, etc.










10 TV, VCR/DVD, ppt projector for awareness raising










11 papers, etc for workshop










12 small grants for fishery groups










13 Car maintenance (Petrol, insurance, radio subscription, check-up, etc.) & mainteneance fees for a photocopier










14 for production of dissemination materials










15 See activity notes










16 See activity notes










17 PMU inputs (15%)










18 See activity notes










19 See activity notes










20 papers, etc for workshop










21 for production of dissemination materials










22 for Mid-term Evaluation and Terminal Evaluation










23 PMU inputs (10%)










24 for the inception workshop










25 for the inception workshop










26 Office machinery and furniture










27 papers, etc for project management










28 computers for Admin and Finance Assistants (USD6000) and VSAT installation (USD8500)










29 Utilities, Security, etc.(20,000/yr -Rent is covered by the Govt.) and VSAT O&M (USD4,000/yr)










30 Office Renovation










31 for NEX audits











Sheet 3: DRC WWF-UNOPS

TOTAL ANNUAL WORK PLAN AND BUDGET






















Award ID: tbd










Award Title: PIMS 1941 - IW – FSP- Lake Tanganyika DRC component (UNOPS Execution)










Project ID: Tbd










Project Title: Partnership Interventions for the Implementation of the Strategic Action Programme (SAP) for Lake Tanganyika










Implementing Partner/Executing Agency: UNOPS






















Activities / Outcomes Responsible Party Fund Code Donor Budget Code Budget Description Year 1 Year 2 Year 3 Year 4 Total Budget Notes
Outcome 1: Sediment discharge reduced from demonstration catchment management sites; providing significant livelihood benefits to local people, and seeking long-term adaptation measures to changing climatic regimes. UNOPS 62000 GEF 72100 WWF Contract 500,000 510,000 510,000 500,000 2,020,000 1



71200 Internationally recruited consultants 0 12,000 12,000 12,000 36,000 2



72200 Equipment and Furniture 26,000 0 0 0 26,000 3



72300 Material and Goods 50,000 75,000 75,000 50,000 250,000 4



73400 Rental & Maint - Other Equip 17,000 17,000 17,000 17,000 68,000 5




SUB-TOTAL OUTCOME 1



2,400,000





TOTAL PROJECT 593,000 614,000 614,000 579,000 2,400,000













Budget Notes:











1 Contract with WWF (Activity Note attached)









2 1 month inputs/yr of international consultant to provide tech backstopping to WWF for yr 2,3, and 4









3 Project Car for DRC component









4 Tree seeds/seedlings









5 Car maintenance (Petrol, insurance, radio subscription, check-up, etc.)








Sheet 4: Burundi UNOPS

TOTAL ANNUAL WORK PLAN AND BUDGET
























Award ID: tbd











Award Title: PIMS 1941 - IW – FSP- Lake Tanganyika Burundi component (UNOPS Execution)











Project ID: Tbd











Project Title: Partnership Interventions for the Implementation of the Strategic Action Programme (SAP) for Lake Tanganyika











Implementing Partner/Executing Agency: UNOPS
























Activities / Outcomes Responsible Party Fund Code Donor Budget Code Budget Description Year 1 Year 2 Year 3 Year 4 Total Budget Notes
Outcome 1. The quality of the water of Lake Tanganyika is improved at two identified pollution hotspots through wastewater treatment. UNOPS 62000 GEF 71400 Locally recruited PMU staff 80,000 80,000 80,000 80,000 320,000 1



71200 Internationally recruited consultants 12,000 24,000 24,000 0 60,000 2



71300 Locally recruited consultants 18,000 30,000 30,000 18,000 96,000 3



72100 Consulting companies 170,000 180,000 50,000 0 400,000 4



71600 Travel 5,000 5,000 5,000 5,000 20,000 5




Learning/Awareness raising/consultation workshops 40,000 50,000 50,000 44,000 184,000 6



72300 Material and Goods 80,000 220,000 0 0 300,000 7



72200 Equipment and Furniture 27,000 90,000 150,000 0 267,000 8



73400 Rental & Maint - Other Equip 0 0 20,000 20,000 40,000 9



73400 Rental & Maint - Other Equip 17,000 17,000 17,000 17,000 68,000 10



72400 Comm & Audio Visual Equip 5,000 0 0 0 5,000 11



72800 IT Equipment 3,000 0 0 0 3,000 12



74200 AV & Printing Production Costs 5,000 5,000 5,000 5,000 20,000 13



74500 Miscellaneous Expenses 1,000 1,000 1,000 1,000 4,000





SUB-TOTAL OUTCOME 1



1,787,000

Project Management UNOPS 62000 GEF 71400 Locally recruited PMU staff 20,000 20,000 20,000 20,000 80,000 14



72200 Equipment and Furniture 6,000 0 0 0 6,000 15



73200 Premises Alteration 7,000 0 0 0 7,000 16



73100 Rental & Maint - Premises 20,000 20,000 20,000 20,000 80,000 17



72800 IT Equipment 5,000 0 0 0 5,000 18



74500 Miscellaneous Expenses 1,000 1,000 1,000 1,000 4,000





SUB-TOTAL Project Management



182,000






TOTAL PROJECT 522,000 743,000 473,000 231,000 1,969,000














Budget Note:











1 PMU inputs (80%) to achieve Outcome 1










2 5 month inputs of internationally/regionally recruited consultants (1 month input = 12,000USD, inclusive of DSA and travel costs) (See activity notes)










3 16 month inputs of nationally recruited consultants (1 month input = 6,000USD). Whenever possible and appropriate, local consultants are hired to assist carrying out tasks assigned to international/regional consultants to build and retain capacities in the country. (See Activity Notes)
4 for the construction of the tertiary wastewater treatment systems










5 PMU staff travel to achive Outcome 2










6 16 workshops (see activity notes)










7 materials for wastewater facility construction










8 Project Car for Burundi component (27,000), 2 machineries (45,000 each) for sewerage pipeline maintenance, laboratory equipments (100,000) and equipments for Pollution Training Center (50,000)
9 Maintenance of the pumping stations










10 Car maintenance (Petrol, insurance, radio subscription, check-up, etc.)










11 Acquisition of TV, VCR/DVD, ppt projector for awareness raising and sensitization campagnes










12 Laptop for Project Manager for Burundi component










13 production of documents for dissemination










14 PMU inputs (20%) to develop Management Information System and to ensure the effective project management










15 For office furnishing










16 For the necessary renovation of the office to meet UN Security standatds










17 For security, etc. (Rental is covered by the Govt)










18 2 desktops for PMU staff











Sheet 5: Regional UNOPS

TOTAL ANNUAL WORK PLAN AND BUDGET






















Award ID: tbd










Award Title: PIMS 1941 - IW – FSP- Lake Tanganyika Regional component (UNOPS Execution)










Project ID: Tbd










Project Title: Partnership Interventions for the Implementation of the Strategic Action Programme (SAP) for Lake Tanganyika










Implementing Partner/Executing Agency: UNOPS






















Activities / Outcomes Responsible Party Fund Code Donor Budget Code Budget Description Year 1 Year 2 Year 3 Year 4 Total Budget Notes
Outcome 1: Regional and national institutions have internalized the implementation of the SAP and FFMP and provide institutional support for the cooperative management of Lake Tanganyika under the ratified Convention. UNOPS 62000 GEF 71100 Internationally recruited PMU staff (CTA&TA) 149,000 149,000 85,000 85,000 468,000 1
71200 Internationally recruited Secretariat Staff (ED&Dir.Envt) 180,000 0 0 0 180,000 2
71400 Locally recruited PMU staff 35,000 35,000 35,000 35,000 140,000 3
71200 Internationally recruited consultants 30,000 36,000 36,000 30,000 132,000 4
71200 Regionally recruited consultants 24,000 24,000 21,000 21,000 90,000 5
71300 Locally recruited consultants 18,000 18,000 0 0 36,000 6
71600 Travel 12,000 12,000 13,000 13,000 50,000 7

Learning/Awareness raising/consultation workshops 100,000 100,000 100,000 88,000 388,000 8
72400 Comm & Audio Visual Equip 5,000 0 0 0 5,000 9
72800 IT Equipment 5,000 0 0 0 5,000 10
71600 Support to LTS - organizing a Conf of Ministers 40,000 0 0 0 40,000
72100 Support to LTS - Translators 30,000 30,000 30,000 30,000 120,000
73400 Support to LTS - Translation equip rental 15,000 15,000 15,000 15,000 60,000
73100 Support to LTS - Utilities 10,000 10,000 10,000 10,000 40,000 11
72200 Equipment and Furniture 27,000 0 0 0 27,000 12
73400 Rental & Maint - Other Equip 17,000 17,000 17,000 17,000 68,000 13
74200 AV & Printing Production Costs 10,000 10,000 15,000 15,000 50,000 14
74500 Miscellaneous Expenses 1,000 1,000 1,000 1,000 4,000

SUB-TOTAL OUTCOME 1



1,903,000
Outcome 2. The quality of the water of Lake Tanganyika is improved at two identified pollution hotspots through wastewater treatment. UNOPS 62000 GEF 71100 Internationally recruited PMU staff (CTA, TA) 49,000 49,000 17,000 17,000 132,000 15
71200 Internationally recruited Secretariat Staff (Dir.Envt) 10,000 0 0 0 10,000 16
71400 Locally recruited PMU staff 35,000 35,000 35,000 35,000 140,000 17
71600 Travel 4,000 4,000 4,000 4,000 16,000 18

SUB-TOTAL OUTCOME 2



298,000
Outcome 3: Sediment discharge reduced from demonstration catchment management sites; providing significant livelihood benefits to local people, and seeking long-term adaptation measures to changing climatic regimes. UNOPS 62000 GEF 71100 Internationally recruited PMU staff (CTA, TA) 73,000 73,000 17,000 17,000 180,000 19
71200 Internationally recruited Secretariat Staff (Dir.Envt) 10,000 0 0 0 10,000 20
71400 Locally recruited PMU staff 35,000 35,000 35,000 35,000 140,000 21
72100 ICRAF Contract 100,000 200,000 200,000 150,000 650,000 22
71600 Travel 4,000 4,000 4,000 4,000 16,000 23

SUB-TOTAL OUTCOME 3



996,000
Outcome 4: Regional monitoring and management systems contribute to the long-term sustainable management of Lake Tanganyika UNOPS 62000 GEF 71100 Internationally recruited PMU staff (CTA, TA) 16,500 16,500 8,500 8,500 50,000 24
71200 Internationally recruited Secretariat Staff (Dir.Envt) 5,000 0 0 0 5,000 25
71400 Locally recruited PMU staff 7,000 7,000 7,000 7,000 28,000 26
72100 IUCN Contract 50,000 50,000 50,000 50,000 200,000 27

SUB-TOTAL OUTCOME 4



283,000
Project Management UNOPS 62000 GEF 71100 Internationally recruited PMU staff (CTA, TA) 34,000 34,000 34,000 34,000 136,000 28
71400 Locally recruited PMU staff 28,000 28,000 28,000 28,000 112,000 29
72200 Equipment and Furniture 18,000 0 0 0 18,000 30
73400 Rental & Maint - Other Equip 10,000 10,000 10,000 10,000 40,000 31
73200 Premises Alteration 8,000 0 0 0 8,000 32
73100 Rental & Maint - Premises 15,000 15,000 15,000 15,000 60,000 33
72800 IT Equipment 10,000 0 0 0 10,000 34
71200 Internationally recruited consultants 0 30,000 0 30,000 60,000 35
74100 Professional Services 7,000 7,000 7,000 7,000 28,000 36
74500 Miscellaneous Expenses 1,000 1,000 1,000 1,000 4,000

UNOPS Management Fee 60,000 60,000 60,000 55,000 235,000

SUB-TOTAL Project Management



711,000





TOTAL PROJECT 1,297,500 1,115,500 910,500 867,500 4,191,000












Budget Notes:










1 CTA:85,000/yr - 50%; TA: 64,000/yr - 40% for the first 2 years









2 ED:110,000/yr - 100% for the 1st year; Director(Env): 70,000 - 70% for the 1st year;









3 Regional Project Coordination Unit (PCU) inputs: 35,000/yr (20%)









4 11 month inputs of international consultants: (1 month input = 12,000USD, inclusive of DSA and travel costs, See details of required inputs in Activity Note)









5 7.5 month inputs of regional consultants (1 month input = 12,000USD, including travel costs, See details of required inputs in Activity Note)









6 6 month inputs of national consultants (1 month input = 6,000USD, See details of required inputs in Activity Note)









7 PCU staff travel to achive Outcome 1 (See Activity Note for PCU travel)









8 18 workshops, including 3 training visits (See description of each workshop in Activity Note)









9 TV, VCR/DVD, ppt projector for awareness raising for Regional component









10 Laptop and other accessaries for CTA









11 Utilities for LTA Secretariat. Rental is covered by the Govt









12 Project car for Regional PCU









13 20,000/yr for Car maintenance (Petrol, insurance, radio subscription, check-up, etc.) & 20,000/yr for simultaneous translation equipment rental









14 production of documents for dissemination, including LTA newsletter









15 CTA:17,000/yr (10%), TA:32,000 (20%) for yr 1&2









16 Dir (Env): 10,000/1st year (10%)









17 PCU inputs:35,000/yr (25%)









18 PCU staff travel to achive Outcome 2 (See Activity Notes for PCU travel)









19 CTA:17,000/yr (10%); TA:56,000/yr (35%) for yr 1&2









20 Dir (Env):10,000 (10%) for the 1st year









21 Regional PCU inputs: 35,000/yr (25%)









22 Contract with ICRAF (See details in the Annex 1 of the Activity Notes)









23 PCU staff travel to support Outcome 3 (See Activity Notes for PCU travel)









24 CTA: 8,500/yr (5%); TA:8,000/yr(5%) for the first 2 years









25 Dir (Env):5,000/yr (5%) for the 1st year









26 Regional PCU inputs: 7,000/yr (5%)









27 Contract with IUCN (See details in Annex 2 of Activity Note)









28 CTA:34,000/yr(20%)









29 Regional PCU inputs (20%)









30 For office furnishing (6,000) and a messenger car (14,000) for RPMU









31 Car maintenance (Petrol, insurance, radio subscription, check-up, etc.) for a messenger car









32 Necessary renovation of the office space









33 For security, etc. (Rent will be covered by Govt)









34 2 desktop & 1laptop & printer for Regional PCU









35 MTE and TE for UNOPS-executed component (Regional, DRC and Burundi)









36 Annual audits for UNOPS-executed component (Regional, DRC and Burundi)