Lake Manzala Engineered Wetland Project
2006
•On September 2006, NIRAS & ECMA modified the monitoring plan (locations, frequencies and parameters). They eliminated the parameters which were not detected during the previous period such as heavy metals and phenol and added some parameters to investigate special processes such as dissolved phosphorus.
•
•On November 2006, In order to increase the level of accuracy, NIRAS & ECMA concentrated the sampling and analysis on three cells with different plant types, different percentage of plant cover and different flows